 |
183rd
Street Improvements |
 |
183rd Street Improvements: LaGrange Rd. (IL Route 45) to 80th
Avenue
Questions/Concerns
from the November 5, 2003 Citizens Advisory Meeting
1.
How are the concerns outlined in the petition going to be incorporated
into the planned roadway?
Answer: The
concerns outlined in the petition have been reviewed by the
Village and Cook County Highway Department, and have also been
incorporated into the discussions at the advisory group meetings.
Where possible, the feedback will be incorporated in to the
design elements of the improvements.
2.
Sound Study: Were decibel levels obtained from both I-80 and
159th Street? How would the decibel levels on 183rd Street
combined with I-80 levels affect subdivisions between the two
roads?
Answer: Noise
levels were collected at residences on streets that are most
representative of what the proposed 183rd Street will be after
the improvements are complete. Noise levels were taken in the
rear yard at homes on 171st Street and 80th Avenue. Noise levels
were also taken on Harlem Avenue (in the front yard) for a
reference and on existing 183rd Street in a rear yard in Pheasant
Lakes for a benchmark. The noise levels are usually taken in
the rear yard, as this is the gathering area. However, noise
levels were taken in the front yard on Harlem as a reference.
Both I-80 and 159th Street are not representative of what is
being proposed for 183rd Street because of the differences
in lane configuration, total traffic volumes and/or truck volumes.
In addition to the noise levels being studied on the streets
mentioned above, existing noise levels were taken on 183rd
Street, which includes any noise created from I-80. A full
analysis of the noise data collected will be performed to show
how the proposed improvements will impact the existing noise
levels on 183rd Street.
3.
How will the Village improve the areas in and around the roadway?
(i.e. sidewalks, landscaping, guard rails, sound walls…)
Answer: The
Village has been proactive when it comes to incorporating decorative
landscaping into the design of the streets in Tinley Park.
A landscaped median is being proposed, which will be planted
with grass and trees, and trees will also be planted in the
parkway between the road and the residences. Guardrails are
not being proposed as part of the improvements. There will
be sidewalks present where they are existing today along 183rd
Street and additional sidewalks will be constructed in front
of Tinley Gardens and extend west to 94th Avenue. Sound walls,
berms and fences have all been discussed at the advisory group
meetings and a further evaluation of these will be done after
the results of the noise analysis are complete.
4.
How will the road be lighted?
Answer: Streetlights
will be installed in accordance with the Illuminating Engineering
Society standards. The possibility of using decorative poles
will be discussed in Phase 2 of the project.
5.
Will there be traffic controls at 92nd Avenue?
Answer: 92nd
Avenue is currently stop controlled at 183rd Street. Stoplights
will only be added if the traffic volumes for the intersection
meet the warrants to justify this addition and the change is
approved by the Illinois Department of Transportation. Both
the Village and the County are committed to monitoring the
traffic volumes to determine the appropriate time to install
necessary controls. This is also the case for 88th Avenue.
Improvements are proposed for 92nd Avenue including widening
the intersection and constructing a left-turn lane from 92nd
Avenue to westbound 183rd Street to alleviate congestion at
the intersection.
6.
Asphalt vs. Concrete?
Answer: The
Cook County Highway Department does not mandate that either
asphalt or concrete be used to construct the roadway. Preliminarily,
183rd Street is proposed to be constructed from asphalt. As
a part of the noise analysis discussed in question 2 above,
the projected noise levels will be studied using asphalt and
concrete construction to see if the type of material used has
a significant impact on the noise created by vehicles on 183rd
Street.
7.
Metra right-of-way:
- Has
Metra approved the right-of-way?
- If
so, where are the documents from Metra memorializing the
right-of-way?
- Where
are the documents from the Village approving the right-of-way?
(Ordinance, Minutes, Correspondence)
- Has
Metra been invited to be a member of this Committee?
- If
not, why not?
Answer: The
Village of Tinley Park must obtain a permanent easement for
constructing the roadway and an at-grade railroad crossing
within Metra right-of-way. The Village is working with Metra
on this matter, but final documents have not been created for
the land usage. The design of the at-grade crossing of the
railroad tracks is mandated by Metra, separate from the design
of the roadway segments within the project limits. The at-grade
crossing will be constructed in accordance with the most current
railroad safety standards.
8.
Funding:
- Who
is paying for the Phase One Study?
- Appropriation
Number
- Have
appropriation numbers been assigned to any IDOT or other
state funding?
- When
will this occur?
- How
will this occur?
- When
will Village request these funds from IDOT
Answer: The
state is funding 70% of the Phase 1 engineering and the Village
is funding the remaining 30%. There are no appropriation numbers
assigned to the money set aside by the Federal Government,
State or Cook County for this project.
9.
Meetings:
- Why
are the meetings now closed to the public?
- How
will residents of 183rd Street be informed of the outcomes
of these closed meetings? (Mail letters to all residents?
Mail minutes to all residents? Place minutes on website?)
- Will
committee reconsider its decision of closing these meetings
to the public?
- Will
Village invite non-represented subdivisions to attend these
closed meetings?
Answer: The
Village of Tinley Park is committed to work with the residents
during the planning stage of the improvements to 183rd Street.
In order for the concerns of the residents to be heard and
discussed formally, an advisory group made up of residents
who reside in subdivisions adjacent to 183rd Street was formed.
The advisory group allows an open discussion between the Village
and the residents regarding topics on a written agenda. Using
this format allows the concerns of the residents to be heard
and discussed. Unfortunately, many of the items on the agenda
from the August 20, 2003 meeting were not discussed at the
meeting. This does not allow the planning process to proceed
as necessary. After discussion with the members of the advisory
group, a decision was made to invite only the advisory group
members to meet and discuss issues that need to be addressed
and attempt to accomplish the goals for the meeting. The consensus
of the advisory group was that the November 5, 2003 meeting
was productive, and that another meeting would be appropriate
in January with a public meeting in February. A document has
been drafted discussing the scope of the project and the issues
discussed at the November 5th meeting. This document will be
signed by all advisory group members and distributed to the
residents in the area. The meeting minutes along with the answers
to these questions will be posted on the Village of Tinley
Park website.
|