MWRD structure rehabilitation/pipelining
The Metropolitan Water Reclamation District of Greater Chicago (MWRD) will perform structure rehabilitation and pipelining along 175th Street and Ridgeland Avenue from June 5 to Nov. 15 in order to update the infrastructure and prevent further deterioration of the existing pipes and structures, which were installed in the 1960s. This is an MWRD project and will incur no cost to the Village of Tinley Park.

Work will be performed by Insituform Technologies USA, with Airy’s, Inc. of Tinley Park as subcontractor for Insituform. Work will involve reconstruction of certain sections of badly deteriorated sewer. Instead of digging up and replacing the old pipeline, Insituform will insert a special lining inside the pipe, creating a new, smooth-surfaced, long-lasting pipe within the old pipe. Repairs are extremely important, as failure of these pipes could result in sinkholes, service interruptions and invasive boring for emergency repairs.

As part of the project, Oak Forest Avenue will be closed to all traffic from 167th Street to the Santa Maria Convent at 6101 Oak Forest Avenue in order to build pipe segments for a bypass system. This portion of the road will be closed for about four weeks beginning June 1 and ending June 30, the road will open on July 1. While this portion of Oak Forest Avenue is closed, a traffic detour will be in effect. Click here to view a map of the detour, which includes routes along 167th Street, Oak Park Avenue, Ridgeland Avenue and 175th Street. Please also note that, during construction, a portion of 175th Street will be down to one lane only.

Due to the depth and diameter of the sewer which is going to be rehabilitated, operations will run 24 hours a day from Monday to Friday. Residents will be notified 24 hours prior to work beginning in their area. Work will not affect sewer service. Certain equipment will be left on overnight, which may result in some noise. Noise is equivalent to the sound of a lawn mower from 100 feet away.

Certain smells associated with styrene, a substance used in construction, may be present. Residents are advised to open their windows to dissipate any smell that enters their homes. Residents also may encounter intermittent sewer smells. Residents can pour a cup or two of water into each basement floor drain to keep the “trap” full, which prevents sewer odor from coming into your home. Because the water evaporates, this should be done regularly.

Overnight lights will be used but are not expected to be a nuisance to residents.

The Village’s Freedom Pond project and Bremen High School District 228’s turf field project at Tinley Park High School will be occurring in the same area. The Freedom Pond project will primarily send its trucks southbound on Ridgeland Avenue, and the turf field project will send its trucks primarily eastbound on 175th Street. All construction trucks are required to use Cook County roads due to weight restrictions.

For more information, please call Insituform Technologies USA at (708) 326-5101.